The conceptual and site plans are complete. Regulatory agencies issued permitting. Additional elements that were added as site improvements include; potable water well and treatment system, electrical system, and wastewater septic treatment system for restroom. Project construction is on hold pending County budget review.
|
| Top |
| |
| Projected schedule dates are for planning purposes only and are subject to change. |
| Start |
Project Summary/Task |
Finish |
Completion % |
| 05/2007 |
Planning |
08/2007 |
100% |
| 08/2007 |
Design |
10/2007 |
100% |
| 03/2010 |
Pre-Construction/Bidding |
06/2010 |
85% |
| 07/2010 |
Construction |
01/2011 |
0% |
| 01/2011 |
Final Completion/Close-out |
02/2011 |
0% |
| |
|
|
|
| |
|
Theo Adkins
Steve Caporusso
Jane Cooper
Adam Hill
|
Dewey Leidal
Barbara Ray
Barbara Meyer, Liaison |
| |
Top |
| |
|
Upcoming Committee Meeting dates and times can be found at: http://ww3.brevardcounty.us/calendar/ |
| |
|
| |
|
|
| Committee Minutes can be read with Acrobat Reader. To download Adobe Acrobat Reader go to www.adobe.com. Official Minutes only are posted from meetings where a quorum was met. |
2002
April 24, 2002 |
2001
November 28, 2001
October 24, 2001
September 26, 2001
|
| |
|
|
|
| |
|
|
|
| |
|
|
|
|
| Office: 321.255.4400 • Fax: 321.255.4422 • sbreferendum@brevardparks.com |
|
Revised
July 27, 2010
|
| Top |