Welcome to Brevard County’s Subdivision Review |
| We are the coordinators for the 11 reviewing agencies and will
help guide you through every step of the review and permitting process.
The following pages and documents will explain
the process to you.
All submittals should be delivered to the
Land Development Division for processing.
Please call us at (321) 633-2065 if you have
any questions or concerns. Best wishes as you begin your subdivision
development!
Rebecca Ragain
Land Development Code |
|
|
All checks should be made payable to:
Brevard County Board of County Commissioners
Submittals are to be delivered to the Land Development Division
for processing. |
Subdivision Plan Submittals
Pre-Application Submittal and Conference
Review Period: 10 Calendar Days
Submittal:
a. Land Development Application *
b. Completed and Approved Concurrency form
c. 5 copies of conceptual plans with topographic information
d. Zoning Verification form *
e. Authorization to Act as Applicant *
f. Applicable Fees *
*Associated Forms & Fees
Construction Plan Submittal (Final Engineering)and Preliminary Plat**
Review Period: 15 Calendar Days
Submittal:
a. Land Development Application *
b. Cover Letter
c. 5 Sets of plans with exhibits as required by ordinance
d. 2 Drainage Calculations
e. 2 Boundaries and Topographical Surveys
f. 2 aerials if over 5 acres or 2 tree surveys if under 5 acres
g. 2 D.E.P. Applications (County Sewer)
h. Plat Certificate of Title
i. Applicable Fees *
If revisions are necessary, the comments will be
faxed to the applicant.
Revised plans and cover letter addressing agencies' comments must be
submitted within six months to keep the submittal and review
process active and include comment letter addressing agencies’ comments
(15 calendar days review for revisions).
Upon agencies approval, the plans will be submitted to the Board to approve
or deny (minimum of 2 weeks for scheduling).
**A preliminary plat may be submitted without construction plans only
when it is part of a site plan process.
County Sewer: When the engineering plans are approved by the agencies,
6 sets of plans must be delivered to Water Resources Department.
*Associated Forms & Fees
Pre-Construction
Conference (after Board approval)
Submittal:
a. Cover Letter
b. 9 Sets of approved construction plans if on County Sewer.
(7 Sets of Plans if not on County Sewer).
c. Copies of all regulatory permits or clearance
d. 1 Completed Engineering Inspection Fees form *
e. Applicable Fees *
A construction permit, covering landclearing
and infrastructure construction will be issued at the conference.
*Associated Forms & Fees
Final Inspection, As-Builts and Certification
Submittal:
a. 4 complete As-Builts including paving, drainage, and utilities.
(See checklist for As-Built requirements)
b. Certificate of Completion form by Engineer of Record.
c. Asset Inventory Form (Publicly Dedicated Improvements)*
Final inspection will be conducted after as-builts
are reviewed and accepted.
Letter accepting construction will be issued by Land Development upon
successful inspection.
*Associated Forms & Fees
Final Plat Submittal
Review Period: 15 Calendar Days
Submittal:
a. Land Development Application *
b. Cover Letter
c. Plat Certificate
d. 5 Sets of the Final Plat. Plat must comply with all requirements of Chapter 177,
Part 1, Florida Statutes.
e. Surveyors and Mappers Certification form *
f. Signed and sealed Surveyors Checklist
http://www.brevardroads.us/pdf/survey/finalplatchecklist.pdf
g. Applicable Fees *
Upon agencies approval, the plat will be submitted to the Board to approve or deny.
(If revisions are necessary, the comments will be
mailed to the applicant.) Revised plats must be submitted within six
months to keep the submittal and review process active and valid
(15 calendar days review for revisions).
Upon agencies approval, the plat will be submitted
to the Board to approve or deny ( a minimum of 2 weeks for scheduling).
See Plat Recording Checklist
for information on recordation.
*Associated Forms & Fees
Preliminary
Plat Submittal (used only for site plan process)
Review Period: 15 Calendar Days
Submittal:
a. Land Development Application *
b. Cover Letter
c. Plat Certificate
d. 5 Sets of Preliminary Plat
e. 2 Boundary Surveys
f. Applicable Fees *
*Associated Forms & Fees
Engineering Revision to Approved Plans
Review Period: 15 Calendar Days
Submittal:
a. Engineering Revision Application *
b. 5 Sets of Plans
c. Applicable Fees *
*Associated Forms & Fees
Waiver Request
Review Period: 15 Calendar Days
Submittal:
a. Land Development Waiver Form *
b. 5 Sets of Plans
c. Applicable Fees *
*Associated Forms & Fees