Driveway, Rights-of-Way Permitting, Inspections Impact Fees & Development Cashier Lot Drainage/Engineering Inspections (Refer to Chapter 62 Land Development Regulations) All information presented on the Land Development web site is accurate as of the date posted and may change without prior notice at the discretion of the Board of County Commissioners. You are advised to contact Land Development to verify all current information and fees. Mission: Achieve excellence through effective and efficient customer service. |
|||||||||||||||||||||
|
|||||||||||||||||||||
|
|
|||||||||||||||||||||
Pre-Application Conference Submittal Submittal for Full and Minor Site Plans |
||
| Forms & Fees (Please use this link for all forms.) |
A cover letter addressing all agency comments must be included with submittal (15-calendar day review for revisions). |
Note: Section 62-3205 Time limitations and expiration for review and approval of site development plans; An applicant shall have six (6) months from the date of formal submittal to make all necessary revisions as required by the land development section and various review agencies to receive final approval of the submitted site development plan. Failure to meet this condition will cause the site plan automatically to become "Null & Void" and fees shall not be refunded. An extension may be approved the county development engineer where the applicant provides supporting documentation consistent with the above criteria in section 62-3205, but has not received approval by the end of the six (6) month period.
Pre-Application Conference and Submittal:
a. One (1) Land Development Application b. Five (5) copies of the conceptual plan with topographic information c. Completed LDD 99 - Zoning Verification Form d. Completed Authorization to Act as Applicant - LDD 106 (unless owner is applicant) Applicable Fees - Please refer to Land Development Website All necessary review agencies will be in attendance and/or submit comments. |
Submittal for Full and Minor Site Plans (SP) :a. 1 Land Development Application b. Cover Letter c. Authorization to Act as Applicant(unless owner is applicant) d. 5 Sets of Plans (include landscape and lighting plans) e. 2 Boundary / Topographic Surveys (maximum of six (6) months old) f. 2 Drainage Calculations / Soils report g. 2 Recorded Deeds and all Instruments of Record h. Current & Pending Zoning Actions: BDP, BSP, CUP, Variance, Etc. i. 2 Fire Flow Calculations (or note on plans) j. 1 Completed Impact Fee Application Form k. 1 Approved Concurrency Form l. Zoning Verification Form (LDD 99) Associated Fees - Please refer to Land Development Fees Review Time: 15 Calendar Days
|
Top |
Amended Site Plan and SeverancesAn Amended Site Plan is a Site Plan which has been previously approved but has not yet had a Certificate of Occupancy issued. a. 1 Land Development Application * b. Cover Letter c. Authorization to Act as Applicant (unless owner is applicant) * d. 5 Sets of Plans (including landscape and lighting plans if applicable) e. Zoning Verification form (LDD 99) * f. Current & Pending Zoning Actions: BDP, BSP, CUP, Variance, Etc. g. 2 Drainage Calculations (if applicable) h. 2 Boundary / Topographic Surveys (if applicable, current within 6 months) i. 2 Fire Flow Calculations or note that they are on plans (if applicable) j. 2 Recorded Deeds and all Instruments of Record (if applicable) k. 2 Copies of Tree Surveys per Landscape/Clearing ordinance (for amended site l. 1 Completed Impact Fee Form A * m. Title Ownership and Encumbrance Report (current within 6 months) n. Concurrency Form (if applicable) o. Applicable Fees Please note: Each plan has a different fee. *
Associated Fees - Please refer to Land Development Fees Review Time: 15 Calendar Days
|
Top |
|
a. 9 sets of approved plans b. NPDES forms (if over project is over an acre), FDEP and SJRWMD, all State, Local, c. Engineer's Certified Cost Estimate d. Engineering Inspection Fees Form * e. Applicable Fees * Associated Fees - Please refer to Land Development Fees
|
|
. a. 1 Land Development Application form * b. 1 Survey c. 5 sets of plans d. Approved Occupational License Application / Zoning Use Approval e. Proof of Ownership or lease f. Applicable Fees * Associated Fees - Please refer to Land Development Fees . Review Time: 15 Calendar Days
|
|
. a. 1 Completed Land Development Waiver Form * b. Set of plans or sketch (8 1/2 x 11) c. Applicable Fees *
Associated Fees - Please refer to Land Development Fees Review Time: 15 Calendar Days
|
|
a. 1 Land Development Waiver Form b. Applicable Fees *
Associated Fees - Please refer to Land Development Fees Review Time: 15 Calendar Days
|
|
a. Engineering Revision Application b. 5 Sets of Plans c. Applicable Fees *